I don’t think anyone will be jealous of our threstle board. Shown here with a list of things to do in no particular order:
The header for the connecting door to the main building and the bathrooms has to get put in. The wall is 18″ thick.
Planning for 5″x5″x50″ 1/2″ steel tubing for the header. We’ll need three of them placed together.
Haven’t decided on just what door to use for this, however we do have about 20 to choose from in the basement of the Scottish Rite building.
The old 1950’s commercial dishwasher has to get removed, cut up and thrown away.
Another big job ahead is the installation of ceiling tiles for the reception, librarian’s office, kitchen and portal. The reception ceiling is seriously out of plumb and will need to be addressed. Other issues abound which will have to be fixed before we can start the ceiling tile installation.